HodariQ
Ctrl K
Back to siteBook a demo

Getting started

  • How HodariQ works
  • From the first estimate to the tender
  • Set up your firm
  • Country, currency and dates
  • Users and roles
  • Approvals
  • Sending documents: e-mail and WhatsApp
  • The change log
  • Plans and limits
  • Features and switches
  • Add-on modules
  • What must come first

Contracts

  • Create a contract
  • Commercial terms
  • Key dates and contract states
  • The contract workspace
  • Programme of works
  • Parties
  • Completion and closing
  • Consultant or contractor: the firm and each contract

Bills of Quantities

  • Checking an Excel BoQ
  • Build a BoQ
  • BoQ templates
  • BoQ assemblies
  • Import quantities
  • Lines, sums and totals
  • Units
  • Measurement sheets
  • Explain a quantity
  • Import from Excel
  • How the import reads a file
  • Paste and copy
  • Rates and build-ups
  • Price list, regions and the Price Book
  • Print the BoQ
  • Export to Excel
  • Check before tender
  • Tender, lock and revise
  • Compare revisions

Take-off

  • Drawing sets: Start from Drawings
  • Start a take-off
  • The screen, keyboard and tablet
  • The scale
  • Lengths, areas and counts
  • Rooms: one click or every room
  • Roofs and wall centre lines
  • Doors, windows and symbols
  • Measure the plan
  • Assemblies
  • Heights from sections
  • Zones
  • Send to the BoQ
  • Quantity Register
  • Print the take-off
  • Check a take-off
  • Revised drawings
  • Revision to a variation order
  • Queries to the architect
  • Quick Measure
  • Bar Bending Schedules

Tenders

  • Tender analysis
  • Tenderers and their rates
  • Checks and ranking
  • Award and the tender report

Variations

  • Variation orders
  • Pricing VO lines
  • Approving a variation order
  • VO from revised quantities
  • The VO document and the register
  • Extensions of time

Valuations and certificates

  • The monthly valuation
  • How the certificate is worked out
  • Retention and its release
  • Advance payment and its recovery
  • Liquidated damages
  • Measurement sheets
  • Submitting, certifying and freezing
  • Claimed and certified
  • Printing certificates

Money

  • Invoices and payments
  • Withholding tax and VAT
  • Who owes what
  • Financial statement
  • Cost control
  • Budget line by line
  • Recording costs
  • LPOs (purchase orders)
  • Suppliers and their prices
  • Schedule of materials
  • Subcontracts
  • Subcontractor certificates
  • Cost plans

Site Portal

  • Add your site team
  • On site: the phone pages
  • The daily report from the phone
  • Chats and photos
  • Notifications on the phone
  • Material requests at the office
  • Who approves, and the settings
  • Daily reports at the office
  • Work done, item by item
  • Who sees what

Plant and Equipment

  • The machine register
  • Import machines from Excel
  • Daily log
  • Charge machines to our contracts
  • Fuel
  • Hiring machines out
  • Service and repairs
  • Plant profit and alerts
  • Plant from the site phone

Inbox and Work

  • How the Inbox works
  • Connect the mailbox
  • How e-mails are sorted, summarised and dated
  • Which contract an e-mail is about
  • Check and approve e-mails
  • My work: reply, notes and Done
  • Alerts, the morning e-mail and the contract

Bids and the NeST scout

  • How bids work
  • Bid or no bid, and the documents
  • Results, the win rate and the contract
  • The NeST scout
  • Bid alerts

Team

  • Team: who has how much work

Registers and alerts

  • Bonds, insurance and documents
  • Alerts
  • The dashboard and the financial statement
  • The contractor portal
Ctrl K
Docs/Variations

Extensions of time

The EOT register: requests, the days granted, and the revised completion date that liquidated damages run from.

An extension of time (EOT) moves the contract's completion date later. HodariQ keeps every request in a numbered register; only the days granted count. The completion date with the granted extensions, the revised completion date, is the date liquidated damages start from on the certificates.

Record a request

  1. 1Open Contracts › Extensions of Time and press New, or press Extensions on the contract's Details.
  2. 2Pick the Contract, the Date requested and the Reason: Variation order (extra work), Delay by the employer or the consultants, Exceptional weather, Unforeseen ground conditions, Force majeure or Other.
  3. 3For a variation order, pick the VO that caused the delay under Variation order. Type the Instruction / letter reference (for example the contractor's letter) and, under the form, what delayed the works and the evidence.
  4. 4Type the Days requested. Save: the request takes the next number of the contract, EOT-001, EOT-002 and so on, as Requested.

Grant or reject

Only a Senior QS / Manager decides. Days granted can be fewer than requested; left at 0, Grant gives all the days requested. Grant asks to confirm (the days move the completion date later), records the date decided and who decided. Reject sets the days granted to 0. Back to Requested reopens a decision made by mistake. While a request is open the form shows Completion date as before → after, so you see what granting it would do.

StateCounts in the completion dateCan be changed
RequestedNoYes, everything; can be deleted
GrantedYes, the days grantedNo: Back to Requested first (Senior QS / Manager)
RejectedNoNo: Back to Requested first; cannot be deleted

The revised completion date

Revised completion date = the contract's completion date + the days granted on all granted extensions. Each granted EOT shows the completion date before it and after it, in register order. The contract shows Days granted (EOT), Completion (revised) and Days late: days past the revised completion date up to today, or up to practical completion once it is recorded.

ExampleTwo extensions on a contract due 10/03/2026
EOT-001, exceptional weather: 20 days requested, 14 granted14 days
EOT-002: 5 days requested, granted in full5 days
Completion (contract)10/03/2026
Completion (revised)29/03/2026

With liquidated damages of 50,000 a day, a valuation dated 31/03/2026 was 21 days late before the extensions (1,050,000); with them it is 2 days late, 100,000. See Valuations and certificates › Liquidated damages.

What an extension changes

  • Granting, or sending an EOT back to Requested, brings any draft valuation of the contract up to date at once: its completion date for damages, its days late and its damages.
  • Certified certificates never change: they keep the completion date they were certified with. A later extension that cancels damages already deducted is given back through the next certificate, because damages are worked out to date (see Liquidated damages).
  • Once the Final Certificate is submitted or certified, no extension can be granted, and decided ones cannot be reopened: the damages in the final account are settled.

Good to know

Granting an extension is a contract decision, usually by the architect or engineer on the QS's advice. Record it in HodariQ when it is decided, with the letter reference, so the certificates follow.

← PreviousThe VO document and the registerNext →The monthly valuation

Something unclear? Ask us on WhatsApp: we answer the same day.

On this page

  • Record a request
  • Grant or reject
  • The revised completion date
  • What an extension changes