Cost plans
The elemental estimate before there is a BoQ: costs of past projects, build-ups from the library, quantities from the drawing, stages compared, then checked against the BoQ.
Before there is a Bill of Quantities, the client asks what the building will cost. A cost plan prices it element by element (substructure, frame, roof...), adds preliminaries, contingency and VAT, and gives the cost per m2 of floor area. It stands on its own: no contract is needed. Once the project becomes a contract, the plan is checked against the Contract BoQ.
A cost plan never sends anything to the BoQ. The BoQ is measured (take-off, schedules, sheets) and priced on its own; the cost plan is the estimate it is checked against. A checked plan becomes, in turn, a past project that gives costs to the next cost plans of the same building type.
Make a cost plan
- 1Go to Estimating › Cost Plans and press New.
- 2Type the Project, and choose the Client. Fill Location, Building type (from the list in Configuration › Building Types), Price region (your home region unless it is built elsewhere), Stage (Concept / feasibility, Scheme design or Detailed design), Date, Gross floor area (m2) and Storeys.
- 3On Elements, the usual 18 elements are already listed, each priced per m2 of floor area: Substructure, Frame, Upper floors, Roof, Stairs, External walls, Windows and external doors, Internal walls and partitions, Internal doors, Wall, Floor and Ceiling finishes, Fittings and furnishings, Sanitary appliances and plumbing, Electrical installations, Mechanical installations, Fire protection, External works and drainage.
- 4Price each element: press Use Past Costs when past projects of the type are found, type a Rate, or open the element (the list button at the end of its row) to build its rate from the library or take its quantity from the drawing. Delete the elements the building does not have, add others, and add a Description of what is allowed for.
- 5Check Preliminaries (10%), Contingency (5%) and VAT (the firm's rate) under the elements, and write the Assumptions (prices at today's rates, exclusions such as land, fees and furniture).
- 6Press Print Cost Plan, then Issue to Client.
How it is worked out
| Priced | Amount |
|---|---|
| Per m2 of floor area | Gross floor area x rate. The quantity follows the floor area when it changes. |
| Quantity x rate | The element quantity (typed, or from the drawing), with its unit, x rate. It stays when the floor area changes. |
| Lump sum | The rate is the sum. |
- Building works = the sum of the elements. Each element shows its Per m2 GFA and its % of works.
- Preliminaries = % of the building works; contingency = % of building works plus preliminaries.
- Total (excl. VAT) = works + preliminaries + contingency; VAT = % of that total; Cost per m2 = total excl. VAT / gross floor area.
If the floor area grows to 1,200 m2, the substructure becomes 72,000,000 while the external works stay 20,000,000.
Costs from past projects
The hardest figure of a cost plan is the rate per m2 of each element. HodariQ takes it from your own finished projects: what each element really cost in their BoQ, per m2 of their floor area, brought to the date and the region of the new plan. Nothing is guessed: every figure comes from a BoQ you priced, and the Past Projects tab lists each project and how it was brought to today.
A plan counts as a past project when all of these are true:
- It has the same Building type as the new plan, in the same company.
- Its Contract has a Contract BoQ (a locked BoQ), and at least one of its elements has its bills matched on the Cost Check.
- It has a Gross floor area.
- It is not of the new plan's own contract (that BoQ is the Cost Check of the new plan, not a past project).
- One plan per contract counts: the latest by date. The earlier stages of the same project are not counted again.
For each element of the new plan, each past project with an element of the same name (any case) whose bills are matched gives one figure:
| Step | Figure |
|---|---|
| Cost per m2 then | Total of the element's bills in the past BoQ / past gross floor area |
| Brought to the date | x index on the new plan's date / index on the date of the past prices. The date of the past prices is the contract's Tender date, else its Contract date, else the past plan's date. |
| Brought to the region | x (1 + factor of the new plan's region) / (1 + factor of the past plan's region), with the factor of each region for every type (Price Regions, a factor with no type and no category). The home region and a region without such a factor count 0%. |
| Past low / middle / high | The lowest, the median and the highest of the figures. With an even number of projects the middle is the average of the two in the middle. |
| Projects | How many figures were found for the element (optional column). |
Use Past Costs fills the rate of every element that is priced per m2, has no rate (0), has no build-up and has a past cost, with its Past middle. Typed rates are never touched; clear a rate to take the past cost again. An element priced by quantity or as a lump sum is never filled: a cost per m2 of floor area does not fit it.
The same plan set in Mwanza moves every figure by +10%: A 72,600, B 84,700, C 82,500, middle 82,500. A region factor for one type only (labour -20%) is not used: an element mixes every type.
Good to know
No past project yet? A plan counts once its contract's BoQ is locked and its bills are matched. For finished jobs made before HodariQ, make one plan per job with its floor area and building type, pick its contract and press Match the Bills: it counts from then on, without pricing its elements.
The Cost Index
Configuration › Cost Index (Senior QS / Manager) holds one figure per date: a published building cost index or your own. The index on a date is the figure of the latest date on or before it. When either date has no figure before it, the cost is used as it was and How says *no index*.
Build-up from the rate library
An element's rate can be made of library rates: each rate times how much of it one unit of the element holds. Open the element (the list button at the end of its row) and add lines under Build-up from the rate library: the Library rate, and Per unit of the element. The element's Rate is then the total of the lines and cannot be typed.
- The rate of each line is copied from the library when the rate is picked. A later change of the library does not move an estimate already given; Library Rates in the element takes today's rates again (the plaster at 10,000 makes the rate 61,000).
- The rate of a line can be typed over (a special price for this job).
- A copy of the plan (and Next Stage) keeps the build-ups with their rates. An issued plan refuses any change to them.
Quantities from the drawing
With the take-off (the add-on HodariQ Take-off), a plan whose Contract has drawings takes its quantities from them, before there is a BoQ. Put the scheme drawings on a draft contract to measure them.
- Floor area from drawing (beside the floor area): area measurements of the contract's drawings. The Gross floor area is their total and cannot be typed. Measure the outside of each floor; a void measured as a deduction counts less.
- From drawing in an element: measurements of any kind of the contract's drawings. The element becomes priced by quantity, in their unit, and its quantity is their total (each measurement with its height and times; a deduction counts less).
- All the measurements of one element are of one unit: m2 of wall and a number of windows are refused together.
- While the plan is a draft its quantities follow the drawing: a wall height changed on the drawing changes the plan. An issued plan keeps the figures it was issued with.
- When picked on a cost plan, a measurement shows its figure and drawing, e.g. External walls: 156.00 m2 (A-101 Scheme plan).
Stages and options
- Next Stage copies the plan to the next design stage (Concept › Scheme › Detailed) with the same name, today's date and every element, and sets Compare with on the copy to the plan it came from. Detailed design has no next stage.
- Compare with (on the Compare tab) is any other plan: the previous stage, or another option of the same project (copy a plan, change it, compare the two).
- The Compare tab shows each element in this plan, in the other plan (the element of the same name) and the Change; and the totals with This plan less the other (red when this plan is dearer).
Issue, change, copy
- Issue to Client needs a priced plan (a total above 0). An issued plan is locked; to change it press Back to Draft, or copy it for a new estimate: the copy is a draft with a new reference and all the elements.
- On an issued plan only these still change: the contract, the matching of the bills (Cost Check), the building type, the price region, Compare with and the assumptions. Its figures never.
- Each plan has its own reference, CP-year-three digits.
- The print-out shows the project, client, location, building type, design stage, floor area and storeys, the elements with quantity, rate, amount and per m2, the estimated cost excluding and including VAT, the assumptions and exclusions, and Prepared by (Quantity Surveyor). A plan not yet issued is marked DRAFT.
Cost Check against the BoQ
On the Cost Check tab pick the Contract (also on an issued plan). Its Contract BoQ total appears beside the plan total with BoQ less plan (red when the BoQ is above the plan). Then press Match the Bills: each bill goes to the element its name points to. Each element shows its BoQ amount, the difference and Over % (the difference in % of the element in the plan, red above 5%).
How Match the Bills decides, for each bill not yet on an element:
- A bill of preliminaries, provisional sums, dayworks, contingencies, prime cost sums or the general summary is never matched: in the plan they are the preliminaries and contingency percentages.
- The bill fits an element when one of the element's words is found in the bill name, each word beginning a word of the name (roof fits Roofing, foundation fits Foundations). The words of the usual elements are in the table below; an element of another name is found by its own words (and, the, of, works left out).
- Only elements without bills yet can take a bill. When a bill fits two elements, the one whose word is the first word of the bill wins (Sanitary fittings goes to Sanitary appliances and plumbing, not to Fittings and furnishings). Still two, or none: the bill is left for you.
- The message lists what went where, and the bills left (fit more than one element, or none). Pick those yourself in Priced in BoQ bills.
- A bill counts on one element only: putting it on a second element is refused, so nothing is counted twice.
- Pressing it again changes nothing already matched.
| Element | A bill name with |
|---|---|
| Substructure | substructure, foundation |
| Frame | frame, structural |
| Upper floors | upper floor, suspended slab |
| Roof | roof |
| Stairs | stair |
| External walls | external wall |
| Windows and external doors | window, external door |
| Internal walls and partitions | internal wall, partition |
| Internal doors | internal door |
| Wall finishes | wall finish |
| Floor finishes | floor finish |
| Ceiling finishes | ceiling |
| Fittings and furnishings | fitting, furnish |
| Sanitary appliances and plumbing | plumbing, sanitary, water supply |
| Electrical installations | electrical |
| Mechanical installations | mechanical, air condition, ventilation, lift |
| Fire protection | fire |
| External works and drainage | external work, drainage, site work, landscap(ing) |
The bills on no element are listed under Bills not matched with their total, and Not matched shows the amount beside the BoQ total: bills matched + not matched = the Contract BoQ. BoQ per m2 (the bills matched / floor area) is what the plan gives as a past project.
Concrete work can then be put on the Frame by hand; putting it also on Upper floors is refused.
Good to know
Cost plans come with the Cost Plans feature (Settings › Features, Professional plan), with Configuration › Building Types and Cost Index. QS Officers and Senior QS / Managers make and issue them; Directors read them. Building types and the index are kept by a Senior QS / Manager. Quantities from the drawing need the take-off add-on.
Something unclear? Ask us on WhatsApp: we answer the same day.