Consultant or contractor: the firm and each contract
What the firm is (Settings › We act as) and who each contract acts for (We act for): the money screens, the certificates and who sees what.
HodariQ asks two questions. What is the firm? A consultant QS firm prepares BoQs and certifies valuations; a contractor builds, invoices the employer and controls its own costs. That is set once in Settings › Our Firm › We act as. Then, on each contract: who do we act for on this job? A consultant QS firm usually acts for the employer, but it can also be hired by a contractor to prepare its claims. That is the contract's own We act for, so one firm can do both kinds of job in one database, without a second company.
Where to set it
- 1Settings › Our Firm › We act as: Consultant QS firm, Contractor or Plant hire company. It is the firm's type, and the starting choice of every new contract. The first-day setup asks it too.
- 2A consultant QS firm making a contract in New contract chooses We act for: The employer (we certify the contractor's work) or A contractor (we prepare its claims). A contractor firm is not asked: it acts for itself.
- 3On the contract (Details), We act for sits at the top of Parties. It can be changed until the contract has its first certificate; from then on it is fixed, because the certificates are made for that side.
- 4The contract workspace says it in its header when it is not obvious: We are the employer's QS, or We prepare the contractor's claims.
The four kinds of firm
| The firm | Set as | Sees |
|---|---|---|
| A consultant QS firm | We act as: Consultant QS firm | Contracts, Estimating, certificates, the employer's tools (cost plans, tender analysis, contractor portal). Never the contractor's costs, budgets, LPOs or subcontracts, not even its administrator. |
| A contractor | We act as: Contractor | Contracts, Estimating (pricing, take-off, rates), applications for payment, invoices, costs, budgets, LPOs and subcontracts. When the database becomes a contractor's and no company in it is a consultant firm, Cost Plans and Tender Analysis are switched off; Settings › Features switches them on again. |
| QS and contractor in one firm | We act as: Contractor, and each contract's We act for | Everything. Each contract is on one side: the employer's (we are its QS) or the contractor's (we build it). Costs, budgets and invoices are kept only on the contracts we build. |
| A plant hire company | We act as: Plant hire company | Its machines only: Dashboard, Office, Plant (Machines, Daily log, Hire, Invoices, Workshop, Profit), Registers and Configuration. No Contracts, Estimating, Money or Site menu, no construction settings. |
A plant hire company
- The menus of construction work (Contracts, Estimating, Money, Site, and the configuration of units, trades, regions, Excel layouts, take-off assemblies and BoQ checks) are hidden for its people. A person who also works for a consultant or contractor company of the same database sees them.
- In Plant, what belongs to our own contracts is hidden: the internal rate, Fuel charged to the job, the Move button (a machine goes out through its hire agreement and comes back with Return), the contract of a day of use and Charge to contracts. A machine is In the yard, On hire or in the Workshop.
- Plant › Invoices lists every hire invoice; each hire agreement still has its own.
- The dashboard is the plant's: machines working, on hire (late back and ending within 7 days), in the workshop, services due; for Accounts, Senior QS / Managers and Directors the hire invoiced this month, what is not paid yet, the profit of the year and the utilisation of the month; the overdue hire invoices; every machine with where it is.
- Plant and Equipment must be switched on (Settings › Features).
Good to know
Changing We act as never deletes anything. Contracts that followed the firm's side follow a change between consultant and contractor while they have no certificate; a plant hire company has no side, so its contracts stay as they were.
The three kinds of contract
| Consultant firm, for the employer | Consultant firm, for a contractor | Contractor firm, its own job | |
|---|---|---|---|
| Our firm on the contract | In Consultant QS | In neither box: the contractor is the client, the employer's QS is another firm | In Contractor |
| A certificate | Certified by us in one step: Submit & Certify | An application: Approve & Send to Employer, then Record Employer's Certificate with the figures the employer's QS certified | An application to the employer's QS, or certified in one step, as Settings › Certified by the employer's QS says |
| The certificate PDF says | we certify that the sum ... is due from the Employer to the Contractor | Application for payment; once certified: due from the Employer to the Contractor, with its name | Application for payment; once certified: due from the Employer to us as Contractor |
| Payments | Recorded by hand with Record Payment | Recorded by hand with Record Payment | From the invoice: Create Invoice, then Register Payment |
| Contractor Portal | Yes: the contractor sends its claims online | No | No |
| Budget, costs, LPOs, subcontracts | No | No | Yes, with the Cost Control and Subcontracts feature |
Rules
- Only a contractor firm on a contract it builds (it acts for the contractor, that is itself) gets invoices, the budget, cost control, LPOs and subcontracts. A consultant firm preparing a contractor's claims does not: its fee is billed to the contractor outside the certificate.
- On the contractor's side, a consultant firm's applications always go to the employer's QS to certify. The setting Certified by the employer's QS is a contractor firm's own choice.
- We act for is fixed once the contract has a certificate. Trying to change it then is refused with the message ... has certificates: who we act for can no longer change.
- Changing the firm's We act as in Settings carries along the contracts that had the firm's old choice and no certificate yet; a contract set to the other side on purpose, or with certificates, keeps its own.
- When one database holds two firms, the contractor menus (Costs & Subcontracts) show only for the people of a firm that acts as a contractor.
- LPOs, subcontracts and costs offer only the contracts the firm builds.
- Cost figures (budget, costs, profit) are shown only to the Senior QS / Manager, Accounts and Director roles. A QS Officer never invoices.
Tip
A firm that only certifies for employers never needs to touch We act for: every new contract already acts for the employer.
Something unclear? Ask us on WhatsApp: we answer the same day.