Tender, lock and revise
The life of a BoQ: Draft, Tender, Contract BoQ and Superseded, who may press each button, and what a lock freezes.
A BoQ moves through four statuses. Each move is made only by its button on More > Revisions, tender and lock: an import, a script or a direct change cannot move a BoQ on, so the checks below always apply.
| Status | What it means | Can be changed |
|---|---|---|
| Draft | Being prepared. | Everything. |
| Tender | Issued to tenderers. | Everything: corrections during the tender period are allowed. |
| Contract BoQ | Locked: the priced BoQ the contract is signed on. Its total is the contract sum. | Nothing but the costing link. Changes are variation orders. |
| Superseded | An older revision, replaced by a newer one. | Nothing. Kept as it was, for the record. |
The buttons
| Button | When | Who | What it does |
|---|---|---|---|
| Issue for Tender | Draft | QS staff | Moves it to Tender. |
| Back to Draft | Tender | QS staff | Moves it back to Draft. Approvals already given are cleared. |
| Lock as Contract BoQ | Draft or Tender | The approvers set in Configuration › Settings › Approvals under Lock the Contract BoQ; nobody set: any Senior QS / Manager. The administrator always can. | Checks the BoQ, records the approval and locks it. |
| Unlock | Contract BoQ, contract still a draft | Senior QS / Manager | Back to Tender. Approvals are cleared. |
| New Revision | Draft or Tender | QS staff | Copies it into the next revision; this one becomes Superseded. |
What locking checks
- The BoQ has a total: a BoQ with no priced line is refused.
- Every line that has a quantity has a rate. Otherwise HodariQ lists the unpriced lines (up to 15) by reference.
- Every % addition has its % and the line it is added to.
- The contract has no other Contract BoQ: a contract has exactly one.
- You are an approver. If not, the message names who can lock it. While it waits, More > Revisions, tender and lock shows Waiting for approval and the Approvals tab lists what was given.
After the lock
- The total excluding VAT becomes the contract's original contract sum; approved variation orders are added to it for the revised contract sum.
- The contract can be started only once it has a Contract BoQ (with its contractor and dates).
- Bills, lines, quantities, rates, measurement sheets, the name, date and notes are frozen. The BoQ opens read only in the editor and cannot be deleted. Import, paste, copy, Quick Measure and take-off into it are no longer offered.
- The only thing that may still be set is the build-up used for costing on each item (Link to Build-ups), because it changes no figure of the BoQ.
- Unlock is refused once the contract has started: from then on every change is a variation order.
Revisions
- 1On a Draft or Tender BoQ press New Revision and confirm.
- 2HodariQ copies every bill and line, with their % links and measurement sheets, into Rev A (then Rev B, Rev C...). The new revision keeps the status of the old one and shows Revision of with the BoQ it replaces.
- 3The old BoQ becomes Superseded and read only. It can still be printed and compared.
- Only the newest revision can be revised: a BoQ that already has a newer revision is refused.
- Approvals are not copied: the new revision is locked on its own approval.
- Awarding a tender also makes a new revision, holding the winner's rates (see Tenders › Award and the tender report).
- Compare Revisions shows what changed between a revision and the one before it (see Compare revisions).
Good to know
Something cannot be done yet? Getting started › What must come first lists every such message and what to do.